home *** CD-ROM | disk | FTP | other *** search
/ Almathera Ten Pack 3: CDPD 3 / Almathera Ten on Ten - Disc 3: CDPD3.iso / scope / 126-150 / scopedisk139 / gantt / amigantt.doc < prev    next >
Text File  |  1995-03-19  |  68KB  |  1,439 lines

  1.  
  2.  
  3.  
  4.  
  5.  
  6.  
  7.  
  8.  
  9.  
  10.  
  11.  
  12.                                    AMIGANTT 
  13.  
  14.                             Project Management Tool 
  15.  
  16.                                 Version 3.00.00 
  17.  
  18.  
  19.  
  20.                               Program Description 
  21.  
  22.  
  23.  
  24.  
  25.  
  26.  
  27.  
  28.  
  29.  
  30.  
  31.  
  32.  
  33.  
  34.  
  35.  
  36.  
  37.                                 July 31, 1989 
  38.  
  39.  
  40.  
  41.  
  42.                                    AMIGANTT 
  43.  
  44.                                Table of Contents 
  45.  
  46.  
  47. 1.0  Introduction 
  48.        1.1 Purpose of the software 
  49.        1.2 Features of AMIGANTT 
  50.        1.3 Restrictions 
  51.        1.4 Installing the software 
  52.  
  53. 2.0  Creating a Project 
  54.        2.1 Main Screen
  55.       2.2 Menu Options
  56.           2.2.1  Project Menu
  57.           2.2.2  Window Menu
  58.           2.2.3  Task Menu
  59.           2.2.4  Print Menu
  60.           2.2.5  Sort Menu
  61.                   2.2.6  Misc Menu          
  62.        2.3 Adding the Project Header 
  63.        2.4 Adding Tasks 
  64.             2.4.1 Adding another project as a task 
  65.        2.5 Modifying Tasks 
  66.        2.6 Deleting Tasks 
  67.        2.7 Saving the Project 
  68.  
  69. 3.0  Printing a Project 
  70.        3.1 Printing the Screen 
  71.        3.2 Printing the Project 
  72.             3.2.1 Gantt Chart 
  73.             3.2.2 Task List & Summary 
  74.             3.2.3 Resource Summary 
  75.             3.2.4 Resource Histogram 
  76.  
  77. 4.0  Modifying Existing Projects 
  78.        4.1 Loading the Project 
  79.        4.2 Changing the Header Information 
  80.             4.2.1 Conversion of Costs/Durations 
  81.  
  82. 5.0  Enhancements for version 3.00.00 of AmiGantt
  83.     and known anomolies
  84.  
  85.  
  86.  
  87.  
  88.  
  89.                     AMIGANTT -- Project Management Software 
  90.  
  91.  
  92.                                1.0  Introduction 
  93.  
  94.  
  95. 1.1  Purpose of the software 
  96.  
  97.        AmiGantt was designed to create a simple, interactive method of 
  98.        outlining the tasks required to complete a particular project, using 
  99.        the GANTT chart as the input format. 
  100.  
  101.        There are other programs in the microcomputer world using a similar 
  102.        interface, but none that I could find for the Amiga) and none that 
  103.        had the range of project flexibility I thought a manager would need.  
  104.        Many project management systems systems tend to be rather 'batch'
  105.        oriented and require a fair amount of task and resource planning before
  106.        you ever get to the computer screen.  The intent with AMIGANTT was to
  107.        provide a simple, easy-to-use tool for tracking of tasks, their
  108.        duration, and their resources. 
  109.  
  110.        Because I'm most familiar with the top-down approach to project
  111.        definition -- where the major tasks are broken down to finer 
  112.        and finer levels of description to very simple activities -- it was 
  113.        decided to build the primary interface around a GANTT chart.  In this 
  114.        way, the tasks already entered can be viewed at all times as subsequent 
  115.        levels of detail are added. 
  116.  
  117.        AMIGANTT can run on any Amiga computer (500, 1000, or 2000) under
  118.        Workbench 1.2 and above(!!).  Although it can run without it, the 
  119.        ARP library should be installed in the LIBS: directory before using
  120.        AmiGantt.   
  121.  
  122.  
  123.  
  124.  
  125. 1.2  Features of AmiGantt 
  126.  
  127.        - utilizes a top-down approach to project definition, based on a GANTT 
  128.          chart interface 
  129.  
  130.        - written to make maximum use of the Amiga, it utilizes an
  131.          Intuition-based interface with drop-down menus and Amiga-key 
  132.      replacements to select functions.
  133.  
  134.        - displays the project in a multi-window mode with separate windows
  135.      for the Gantt Chart, task information input, resource histogram
  136.      display and Pert Chart display
  137.  
  138.        - AmiGantt is well behaved in the multi-processing mode and should have
  139.      no problem working with other programs.
  140.  
  141.        - can be run from either Workbench, via the supplied icon or directly
  142.      from CLI.  Users running the program from CLI can optionally 
  143.      provide the name of the input project file they wish to work on.
  144.      AMIGANTT also optionallly creates icons for each project saved,
  145.          which allows Workbench users to directly enter the project simply
  146.          by double-clicking its icon.  With version 3.00.00 and above, 
  147.          a menu selection is provided so the user may have AmiGantt 
  148.          generate or not generate icons for saved projects.
  149.  
  150.        - AmiGantt will notify the user of low-memory situations and provide a
  151.      graceful exit.  It uses a dynamic-memory allocation scheme so that
  152.      only enough space is taken to hold the tasks defined for the
  153.          project.  As tasks are deleted from the project, AMIGANTT will
  154.      free the memory allocated to them.
  155.  
  156.        - up to 500 tasks may be defined for any project and a project may 
  157.          contain other projects as tasks (e.g. sub-projects) 
  158.  
  159.        - text-only entries may be defined to provide headings to help separate
  160.      major tasks, or to provide additional description on the Gantt
  161.      chart 
  162.        
  163.        - Milestone tasks may be defined to identify reaching certain points
  164.      in the project.  Milestones can be tied to a particular date or
  165.      dependant on other tasks.
  166.   
  167.        - the calendar and task fields may be scrolled separately to allow 
  168.          viewing of any part of the Gantt Chart 
  169.  
  170.        - the project format may be displayed as daily, weekly or monthly with 
  171.          conversion routines between each format 
  172.              - sub-projects are also automatically converted 
  173.  
  174.        - any task in the project (except headers) may be dependent
  175.          (cannot start until the first is finished) on up to
  176.      10 other tasks 
  177.  
  178.        - calculated dependencies are supported, so the user may define that
  179.          a task begins 5 days after the end of another task or 2 months
  180.          before the beginning of another task.
  181.  
  182.        - can store planned and actual durations of tasks 
  183.  
  184.        - up to 10 resources may be defined for each task 
  185.              - costs for each resource may be uniquely defined in each task 
  186.              - costs for each resource may defined as 'fixed' (do not change
  187.                   with the duration of the task) or 'variable' (change with
  188.                   with the duration of the task)
  189.              - costs and resources are retained to aid in the adding of new
  190.           tasks 
  191.  
  192.        - task start dates may float based on other task dependencies or the 
  193.          project start date, or a start date may be specified
  194.  
  195.        - tasks may optionally have an 'ending date' attached which will
  196.      become the latest end date for the task.  This allows tasks to
  197.      include a 'float' period if this end date is beyond the time
  198.      needed for the task.
  199.  
  200.        - printouts available include  
  201.              - Screen image 
  202.              - Gantt Chart 
  203.              - Resource Histogram 
  204.              - Resource Summary 
  205.              - Task Listing (Detail) 
  206.              - Task Summary
  207.        
  208.        - printouts may be aborted by pressing the ESC key at any time. 
  209.  
  210.        - printouts for the Gantt Chart, Resource Histogram, and Pert Chart
  211.          may be printed in Graphic bitmap mode or in text mode, depending
  212.          on the characteristics of the printer. 
  213.  
  214.        - using the Amiga Preferences program, graphics printouts may be 
  215.          printed horizontally or vertically.
  216.  
  217.  
  218. 1.3  Restrictions of AmiGantt 
  219.  
  220. NOTE -- These are restrictions placed on version 3.00.00 of AMIGANTT.  They 
  221. may be removed in subsequent releases of the software. 
  222.  
  223.        - 500 tasks per project 
  224.        - 10 dependent tasks per task 
  225.        - 10 resources per task 
  226.        - task descriptions are limited to 30 characters each 
  227.        - resource descriptions are limited to 15 characters each 
  228.        - resource cost per unit (day/week/ or month) cannot exceed $9999.99 
  229.  
  230.  
  231.  
  232.  
  233. 1.4  Installing the software 
  234.  
  235.        AmiGantt consists of a single program file, called AMIGANTT, which can 
  236.        be placed anywhere the user desires.  In most cases, installation will 
  237.        simply consist of copying this file into the desired directory.
  238.        WorkBench users may simply drag the AmiGantt icon included on the
  239.        diskette to the desired drawer.   
  240.  
  241.        Project files created by AmiGantt are placed according to the user's 
  242.        wishes and hence, may also be located on any convenient disk volume. 
  243.  
  244.        It can be run from either CLI or Workbench and an icon file has been 
  245.        provided for the latter (appropriately enough, called AmiGantt.info).
  246.        The icon file should be copied to the same directory as the AmiGantt
  247.        program.  
  248.  
  249.        Verson 3.00.000 of AmiGantt and above make use of some of the 
  250.        features provided by the ARP library (AmigaDos Replacement Program)
  251.        such as the file requestor and the CLI startup processing.  In 
  252.        order to support these features, version 34 of the ARP library
  253.        must be installed in the LIBS directory of your system disk.  A
  254.        copy of this library, called arp.library is provided on the disk.
  255.        This file should be copied to LIBS: and your Amiga re-booted before
  256.        using AmiGantt 3.00.00.
  257.  
  258.  
  259.  
  260.                     AmiGantt -- Project Management Software 
  261.  
  262.  
  263.                             2.0  Creating a Project 
  264.  
  265.  
  266. 2.1  Main Screen 
  267.  
  268.        When the program is first started, the first thing the user will see
  269.        is the Main Screen of AmiGantt.  The screen shows a blank task list
  270.        and calendar area. 
  271. ______________________________________________________________________________    
  272. |7| AmiGantt 3.00.00                                    |   |   |
  273.                Apr'88 11111 11222 22222 May'88 1111 11112 22222 33
  274. ___                     12345 89012 56789 23456 90123 67890 34567
  275. |*|1  Task descriptions                                 ^
  276. |*|2                            |
  277. |*|3                        Date Calendar
  278. |*|4
  279. |*|5
  280. | |6
  281. | |7
  282. | |8
  283. | |9
  284. | |10
  285. | |11
  286. | |12
  287. | |13 <--- Task numbers
  288. | |14
  289. | |15
  290. | |16
  291. | |17
  292. | |18                    Date scroll gadget
  293. | |19                          |
  294. | |20                          |
  295. | |                          |
  296. | |<-- Task scroll gadget  _______________________|__________________________ 
  297. |_|________________________|_________________________________________________|
  298.  
  299.  
  300.  
  301.  
  302.  
  303.  
  304.  
  305. 2.1  Main Screen (Cont'd) 
  306.  
  307.        The Calendar on the main screen is defaulted to the daily format and 
  308.        will begin on the Monday previous to or on the current system date -- 
  309.        which is usually today.  The top left corner of this screen will 
  310.        display the version number of AmiGantt. 
  311.  
  312.        Below the title line is the main body of the AmiGantt Gantt Chart.  
  313.        The numbers on the left side of the screen are the task numbers for 
  314.        each of the lines in the Gantt Chart.  These numbers are used as 
  315.        reference in AmiGantt and should be used when describing dependencies 
  316.        between tasks.  Immediately to the right of the numbers is where a 
  317.        portion of the text description of each task will be displayed.  Have 
  318.        no fear, the full task description is provided on all printed output. 
  319.  
  320.        To the right of the descriptions will appear the task duration bars, 
  321.        showing when the task occurs on the calendar.  In some cases, tasks may 
  322.        extend beyond the right side of the screen or may even start on a date 
  323.        beyond the right edge.  To view the task pointers for these, the date-
  324.        slider gadget at the bottom of the screen may be used to shift the
  325.        calendar 'window' to the right or left.  You can also shift the 
  326.        calendar display left and right 1 week at a time using the right and 
  327.        left cursor keys.  Note though, that the calendar will not shift beyond
  328.        the project starting or ending dates.
  329.  
  330.  
  331. CURRENT TASK --
  332.        The orange block shown in the task area highlights the 'current task'.
  333.        Any task operation, such as add, modify, or delete will operate on this 
  334.        highlighted 'current task'.  The current task may be changed by either
  335.        moving the highlight block up or down using the cursor positioning keys;
  336.        or by placing the mouse pointer anywhere in the description field of 
  337.        the desired task and pressing the left mouse button.
  338.  
  339.        You can scroll the task numbers in the display using the task scroll
  340.        gadget at the left of the screen.  It is possible to scroll the current
  341.        task off the displayed portion of the screen.  AmiGantt keeps track of
  342.        the current task though, and will highlight it when it appears on
  343.        the screen again.
  344.  
  345.        If you use the cursor positioning keys to select the current task, the
  346.        task display will automatically scroll up or down (if possible) when
  347.        you hit the top or bottom of the display -- in order to keep the
  348.        current task visible.
  349.  
  350. 2.2  Menu Options
  351.  
  352.        As with any good Amiga program, AmiGantt functions are selected using
  353.        the drop-down menus displayed when the right mouse button is pressed.
  354.        There are six sets of menus available in AmiGantt:  The PROJECT menu,
  355.        WINDOW menu, TASK menu, PRINT menu, SORT menu, and the MISC menu.  The
  356.        various functions available in AmiGantt are logically collected under
  357.        these menus and are described below.  For those users more comfortable
  358.        on the keyboard, there are Amiga-key replacements for the major
  359.        options.
  360.  
  361. 2.2.1  Project Menu
  362.  
  363.        This menu deals with functions that affect the entire project that is 
  364.        being worked on.  It also includes some information about AmiGantt and
  365.        the ability to quit the program.  Each of the options found in this
  366.        menu are described below.
  367.  
  368.            
  369.      Load Project (Amiga L) 
  370.        To continue work on an already defined and saved project file, 
  371.        select Load Project and then fill in the name of the project file
  372.        to be loaded into AmiGantt.  More information on saving and loading
  373.        of project files is provided in section 2.6 of this manual. 
  374.  
  375.      Save Project (Amiga S) 
  376.        Save Project allows the user to save the latest contents of the
  377.        project to a file on disk.  If a previous project was Loaded into
  378.        AmiGantt for modification, Save will assume you want to use the same
  379.        file name again and will prompt to ask if it's OK to wipe out the
  380.        existing project file.  If no file was previously loaded, Save will
  381.        prompt the user to provide a suitable name for the project to be
  382.        stored on disk and to write out the project tasks to that file.
  383.        This file may then be loaded back into AmiGantt at any time (see
  384.        Load Project above) for revision or update.
  385.  
  386.      Save As 
  387.        This option allows the user to save the project to disk by directly
  388.        asking for the file name he/she wishes to use.  Again, if need be, 
  389.        AmiGantt will prompt to ask if it's all right to overwrite an existing
  390.        file.
  391.         
  392.      New Project (Amiga N) 
  393.        By selecting New Project, the user can remove all tasks from 
  394.        the project and start with a clean slate.
  395.        
  396.      Info
  397.        Selecting this option from the Project menu will display a window
  398.        with the current version number of AmiGantt and some information on
  399.        how to get in touch with the author.
  400.  
  401.      Quit (Amiga Q)
  402.        Selecting the Quit option from the Project Menu allows the user
  403.        to leave AmiGantt.  The same action may be accomplished by hitting the 
  404.        close window gadget at the top left of the Task (or Gantt) Window.
  405.        If there were changes to the project and it has not been saved lately,
  406.        AmiGantt will notify the user that changes to the project may be lost 
  407.        and will give the option to go back into AmiGantt and Save the
  408.        project before exiting.  Selecting the Cancel gadget in the 'Want to 
  409.        Leave?' requestor will return the user to normal AmiGantt main screen
  410.        with the option to select the Save or Save As menu options. 
  411.  
  412.        If the user wishes to ignore the changes made to the project, he 
  413.        should select the OK gadget from the requestor.
  414.  
  415.          
  416. 2.2.2  Window Menu
  417.  
  418.        AmiGantt contains three main windows for display of the task
  419.        information provided for a project.  They are: a) the Gantt (or Main)
  420.        window, b) the Resource Window, and c) the Pert Window.
  421.  
  422.        Pert Chart
  423.        When this function is selected, AmiGantt will open an additional 
  424.        window which will display the real-time updated Pert or Network chart
  425.        for the project.  Along the bottom of the window is a date scroll
  426.        gadget which can be used to change the range of dates shown.  The dates
  427.        shown in the window can also be changed a week at a time using the
  428.        right and left cursor positioning keys.
  429.  
  430.        In later versions of AmiGantt, the user will be able to interact with
  431.        this window as well to change the dependencies and interconnection of
  432.        tasks within the project.
  433.  
  434.        Resource Histogram
  435.        As with the Pert Chart function above, selection of this option will 
  436.        cause AmiGantt to open an additional window which will display the 
  437.        current resource allocation for the project in histogram format.     The
  438.        Resource Window function will also open a Legend Window which displays
  439.        the pattern used in the histograms for each of the project resources
  440.        used within the time period shown in the window.
  441.  
  442.        Along the bottom of the window is a date scroll gadget which can be 
  443.        used to change the range of dates shown.  The dates shown in the window
  444.        can also be changed a week at a time using the right and left cursor
  445.        positioning keys.
  446.        
  447.  
  448.        The windows have all the usual gadgets assigned so that they may be
  449.        moved or resized.  There are no menus assigned to either of the
  450.        windows, but they may be closed by clicking on the close-window gadget
  451.        in the top left corner.
  452.  
  453.  
  454. 2.2.3  Task Menu
  455.  
  456.        Functions in this menu allow the user to define, delete, and modify
  457.        the tasks contained within a project.  It also allows him/her to 
  458.        modify the default header information created for each project.
  459.  
  460.        NOTE (again)  It is STRONGLY URGED THAT THE USER FIRST SET UP THE 
  461.        PROJECT HEADER by selecting the Modify Header option from this menu
  462.        before proceeding with the addition of new tasks.  See section 2.3
  463.        of this manual regarding the addition (modification) of the project
  464.        header.
  465.  
  466.      Add Task (Amiga A) 
  467.        This option is selected to add new tasks to a given project.  
  468.        More information on adding a task is provided in section 2.4 of 
  469.        this document.  It should be noted, though, that AmiGantt works 
  470.        on an 'insert before' mode of task addition.  In other words, if 
  471.        the current task block is on a task number that has no description
  472.        for it and Add Task is selected, AmiGantt will add that task
  473.        number.  If the current task block is positioned over a task number 
  474.        that does have a description and Add Task is selected, then
  475.        AmiGantt will push all the tasks at the cursor position and below,
  476.        down one line on the screen and insert the new task at that
  477.        position.  Again, more information on this will be provided in
  478.        section 2.4. 
  479.  
  480.      Delete Task (Amiga D) 
  481.        The user can remove a task by setting the current task block over a
  482.        task description and selecting Delete Task.  Before actually
  483.        removing the task, AmiGantt will present the entire task
  484.        description and give the user the option to gracefully back out.
  485.        If you really want to remove the task, select the OK gadget at the
  486.        bottom left of the task window.  If you thing better of it and want to
  487.        keep the task, select the CANCEL gadget at the bottom right of the 
  488.        window.
  489.  
  490.      Modify Task (Amiga M) 
  491.        By setting the current task block over a previously defined task, and
  492.        selecting Modify Task, the task fields are presented for changes. When
  493.        the desired changes have been made, click on the OK gadget at the 
  494.        bottom left of the task window.  If you change your mind and don't 
  495.        want to make any changes to the task, click on the CANCEL gadget at 
  496.        the bottom right.
  497.   
  498.      Move Task
  499.        NOTE -- This option is not available in version 3.00.00 of AmiGantt.
  500.        When functioning, it will allow the user to pick up a task and move
  501.        it to another place in the Gantt Chart listing.
  502.      
  503.      Modify Header (Amiga H) 
  504.        Each project contains a 'header' that contains global information 
  505.        about the project.  More information about the header information 
  506.        is contained in section 2.3 of this manual.  Selecting Modify Header
  507.        allows the user to view and modify this global information.  
  508.        IT IS STRONGLY RECOMMENDED THAT THIS OPTION BE SELECTED FIRST 
  509.        WHEN STARTING A NEW PROJECT -- BEFORE PUTTING IN ANY TASKS. 
  510.  
  511.  
  512. 2.2.4 Print Menu
  513.     
  514.        This menu allows the user to select various options for output of
  515.        reports from AmiGantt.  During the operation of these options, the
  516.        mouse pointer image will change to that of a printer with PIP (Print In
  517.        Progress) at the bottom.  This is to remind the user that AmiGantt
  518.        will not process any other functions until the printing is complete.
  519.        At any time during the printing process, the user can cancel the
  520.        printout by pressing the    ESC key on the keyboard.
  521.  
  522.      Output to...
  523.        When selected, this option presents a sub-menu with two further
  524.        options.  It allows the user to select whether print output should be
  525.        routed to the PRT: (Preferences Printer) device or to a file on disk.
  526.        The options are mutually exclusive and operational for all output from
  527.        AmiGantt.
  528.  
  529.        If output to a file is selected, a file requestor window will be 
  530.        presented, asking the user for the name of a file in which to store
  531.        the output reports.
  532.  
  533.        Just a note here -- Output to a file will not prompt if the 
  534.        file already exists (this will be added in a later release) so 
  535.        selection of a second report will wipe out the first.
  536.  
  537.      Print Type
  538.        When selected, this option presents a sub-menu with two further
  539.        options.  It allows the user to select whether print output should be
  540.        of a 'textual' type (using normal ASCII characters to generate the
  541.        Gantt, Pert, and Resource reports) or a Graphic Bit-Map type (where
  542.        an graphical image of the Gantt, Pert, and Resource charts, similar
  543.        to the display on each of the windows but without the gadgets).
  544.        The options are mutually exclusive and operational for all output from
  545.        AmiGantt.
  546.  
  547.      Print Screen
  548.        As would be expected by the description, selecting this option with
  549.        the Output to... option set to PRT: will    cause a screen 'dump' of what
  550.        is currently being displayed to be routed to the user's default
  551.        printer.  If the Output to... option is set to file, AmiGantt will
  552.        create an IFF file for each of the windows (Gantt, Resources, and Pert)
  553.        that are being displayed at the time.  As the files are being created,
  554.        each window will be brought to the front of the display as it is being
  555.        saved. 
  556.  
  557.      Print Project 
  558.        Selection of this option causes AmiGantt to generate a complete
  559.        printout of the entire project, including Gantt charts, task listings,
  560.        resource histograms and the Pert Chart.  More information regarding the
  561.        project printouts is provided in section 3.2 of this manual. 
  562.  
  563.      Print Tasks
  564.        Selecting this option provides printouts of the Task Summary and 
  565.        complete Task List of the Project.  Examples of these two reports
  566.        are provided in section 5 of this document.
  567.  
  568.      Print Resources
  569.        This option prints out the Resource Histogram and Project Summary.
  570.        More information on these  project reports and examples are found in
  571.        sections 3.2 and 5.0 of this manual.
  572.  
  573.      Print Gantt Chart
  574.        Selecting this option provides the user with just a printout of the
  575.        project Gantt Chart, similar to the display on the main screen.
  576.  
  577.      Print Pert Chart
  578.        This option will print out the network chart of the project.
  579.  
  580.  
  581. 2.2.5 Sort Menu
  582.  
  583.        By selecting any of these options, the tasks in the project will be
  584.        sorted and re-ordered in the display according to the criteria
  585.        selected.
  586.  
  587.      Sort by Starting Date
  588.        In this option, the tasks will be sorted and displayed in 
  589.        ascending order of each task's earliest starting date.  Headers 
  590.        and Milestones are placed at the end of the task list.
  591.  
  592.      Sort by Competion Date
  593.        Here, the tasks are sorted and displayed in ascending order of the 
  594.        latest ending date of each task.  As with the sort by Starting
  595.        Date, Headers and Milestones are placed at the end of the task
  596.        list.
  597.  
  598.      Sort by Critical Path
  599.        In this option, AmiGantt will examine the list of tasks and determine
  600.        those that form the Critical Path through the project.  For AmiGantt, 
  601.        the Critical Path is defined as the set of tasks that form a continuous
  602.        path from the begining to the end of the project.  If there are
  603.        multiple paths, the one with the longest duration is taken as the 
  604.        Critical Path.  The tasks in the Critical Path are then floated to the
  605.        top of the task display.  The order of other tasks is maintained and 
  606.        they are displayed below the last task in the Critical Path.
  607.  
  608.  
  609. 2.2.6  Misc Menu
  610.        Options on this menu allow the user to select whether AmiGantt will 
  611.        automatically create icons for projects that are saved.  The user can
  612.        also select whether AmiGantt identifies tasks on the Critical Path by
  613.        changing the colour of their bars in the Gantt Chart.
  614.  
  615.  
  616. 2.3  Adding the Project Header (Modify Header from Task Menu) 
  617.  
  618.        As mentioned in section 2.1, each project contains a 'header' which 
  619.        holds certain global information about the project.  The types of 
  620.        information stored in the header are: 
  621.              a) a description of the project 
  622.              b) the start date of the project and 
  623.              c) the type of calendar used in the project (it can be daily, 
  624.                 weekly or monthly) 
  625.  
  626.        When Modify Header is selected from the Task Menu, AmiGantt will 
  627.        present the Header Modification window and allow the user to modify
  628.        these global values. 
  629.  
  630.        If you are just starting out in a new project, the fields displayed
  631.        here will be set up with some initial default values.  The Description
  632.        fields will be blank, the Project Start Date will be set to the
  633.        current system date, and the Calendar will be set to 'D' for Daily
  634.        format. 
  635.  
  636.        If a previously defined project was loaded using the Load Project
  637.        selection from the Project Menu (see section 4.1), then these fields
  638.        will display the values retrieved from the project file. 
  639.  
  640.      DESCRIPTION - 
  641.        The Project Description field consists of 3 lines of 40 characters
  642.        each in which you may place any descriptive information you wish about
  643.        the project.  Since the first line of the description will be used as
  644.        title for the project and will be displayed in the top line of the
  645.        Main Screen, it is suggested that this first line contain some sort of
  646.        appropriate title for the project as a whole. 
  647.  
  648.        The Description field will accept any characters, alpha or 
  649.        numeric, in upper or lower case.  If you wish, any or all of the 
  650.        description lines may be left blank.
  651.  
  652.      START DATE - 
  653.        This field describes the overall start date for the project.  As 
  654.        mentioned above, it is defaulted to the current system date, but 
  655.        you may change this to any value you wish.  The date provided 
  656.        here will be used by AmiGantt to modify the calendar display on 
  657.        the Main Screen -- re-setting the first calendar entries on the 
  658.        left side of the screen starting with the project start date. 
  659.  
  660.        This field also interacts with the Calendar field below it, in 
  661.        that a Daily Calendar will use the exact date provided as the 
  662.        project start date; a Weekly Calendar will take the Start Date if 
  663.        it's a Monday, or move it to the previous Monday; and a Monthly 
  664.        Calendar will move the Project Start Date to the first of the 
  665.        month for display purposes. 
  666.  
  667.        The entry in this field is input in standard YYYYMMDD format where
  668.        YYYY is the four digit year, such as 1988; MM is the two digit 
  669.        number of the month, such as 07 for July; and DD is the two digit
  670.        number for the day of the month, such as 29. (It was done this way
  671.        to make it easier for AmiGantt to do sorting and comparisons).
  672.        Only numeric values are accepted in each of the fields and the
  673.        date is validated to make sure it is a real date (i.e. not the
  674.        31st of February). 
  675.  
  676.      CALENDAR - 
  677.        This field specifies the type of calendar entries the project 
  678.        will use.  If 'D' for Daily is selected, the project accounting 
  679.        and record keeping will provide for input on particular days and 
  680.        all displays and reports will provide daily information.  If 'W' 
  681.        for Weekly is selected, AmiGantt will deal with project tasks and 
  682.        entries on a weekly basis, with the smallest valid time unit being 1
  683.        week.  As you might expect, the 'M' Monthly calendar provides for
  684.        AmiGantt looking at the project from a monthly perspective. 
  685.  
  686.        After the user has made the appropriate changes, he should select the
  687.        OK gadget in the lower left of the window to make the modifications to 
  688.        the project header.  If he decides not to make changes at this time,
  689.        he should select the CANCEL gadget in the lower right of the window to
  690.        return to the Main Screen. 
  691.  
  692.        NOTE -- The user can also move from field to field in the Header
  693.        Modification window by pressing the RETURN key.  However, pressing 
  694.        RETURN after the Calendar field will have the same effect as selecting
  695.        the OK gadget.
  696.  
  697.  
  698. 2.4  Adding Tasks  
  699.  
  700.        After the project header information has been updated to set up the 
  701.        global environment for the project, the next step is to start adding 
  702.        the individual tasks that make up the project.  AmiGantt has been 
  703.        designed to let the user work in a top-down manner in defining the 
  704.        project -- setting out the major tasks to be accomplished, then 
  705.        providing finer and finer detail of sub-tasks to be completed. 
  706.  
  707.        AmiGantt works on an 'insert-previous' mode for determining the 
  708.        placement of tasks.  While the user does not have to specify the number 
  709.        of the task (AmiGantt handles this automatically), the current task
  710.        block (see section 2.1) is important in determining where the task will
  711.        be added. 
  712.  
  713.        When adding a task to a project, the user should position the current
  714.        task block over one of the tasks shown at the left of the screen. 
  715.      
  716.        If the block is positioned on a line with no existing entry (i.e. the 
  717.        description shown to the right of the number is blank) and Add Task is
  718.        selected, then AmiGantt will insert the task at the number shown on
  719.        that line.  If, on the other hand, the block is positioned on a line
  720.        with an existing entry and Add Task is selected, the the task will be
  721.        inserted    before the existing task entry.  (Actually, the new task will
  722.        be added    at the task number on that line and all others after it will
  723.        be pushed down one line, giving them task numbers one larger, but the
  724.        apparent    effect is that of inserting before the current task). 
  725.  
  726.        Once a task number has been highlighted and Add Task has been selected, 
  727.        AmiGantt will present the Add Task window, where the user may fill in
  728.        the pertinent information about the task. 
  729.  
  730.        If the user decides that he did not really want to add a task at this
  731.        time, selecting the CANCEL gadget at the bottom right of the window
  732.        will return him to the Main Screen. 
  733.  
  734.  
  735.      DESCRIPTION - 
  736.        The Task Description field is an alpha-numeric field of 30 
  737.        characters in which a short description of the nature of the task 
  738.        can be provided.  Although only the first 20 or so characters of 
  739.        this description will be shown on the Main Screen, all reports 
  740.        will show the entire description.  The user may input any 
  741.        information in this field.  IT IS STRONGLY URGED THAT SOME SORT OF
  742.        NON-BLANK DESCRIPTION BE PROVIDED FOR EACH VALID TASK. 
  743.  
  744.      START DATE - 
  745.        As with the Project Start Date described in the 'Adding the Project
  746.        Header' section of this manual, the task start date defines an
  747.        absolute starting date for the task.  It is in the same YYYYMMDD
  748.        format and is validated for things like a month number of 13, days
  749.        beyond 31, etc. 
  750.  
  751.        In the case of the Task Start Date though, leaving the date field 
  752.        blank has a special meaning.  It allows the task to 'float', with its
  753.        actual start date changing, depending upon other tasks or the Project
  754.        Start Date.  If a task is specified with a blank start date and it is
  755.        not dependent on any other tasks, then the actual start date of the
  756.        task will float with the Project Start Date.  That is, the task start
  757.        date will be assumed to be the same as the Project Start Date and will
  758.        change automatically with any changes made to the Project Start Date
  759.        via the Modify Project Header selection. 
  760.  
  761.        If a blank Task Start Date is specified and this task is dependent on
  762.        other tasks (i.e. it cannot start until other tasks have been
  763.        completed) then the actual start date of the task will float with the
  764.        completion of the other dependent tasks.  So, if Task 2 (which we are
  765.        working on) is dependent on Task 1 (meaning Task 2 can't start until
  766.        Task 1 is completed), then Task 2's starting date will become the day,
  767.        or week, or month -- depending on the project calendar -- after
  768.        Task 1 is scheduled to complete.  If we change Task 1's start date or
  769.        duration, then Task 2's start date will be automatically updated. 
  770.  
  771.      END DATE -
  772.        As with the START DATE field, entries here should be in the same
  773.        YYYMMDD format.  Values for this field need not be supplied unless
  774.        you want to set an absolute 'must finish by' date for this task.
  775.        AmiGantt will interpret this field to be the latest possible end
  776.        date for the task.  When displaying this task in the Gantt chart
  777.        this entry will also be used to determine if there is any 'float
  778.        time' between the starting date of the task, plus its duration,
  779.        and the end date supplied.  If there is excess, AmiGantt will 
  780.        display this 'float' period as a set of dots on the Gantt Chart.
  781.        Leaving this field blank simply means that the end date for the
  782.        task will be determined by the start date plus the duration.  Any
  783.        changes in the start date (due to task dependencies, etc.) will be
  784.        automatically reflected in a new end-date for the task.
  785.  
  786.      DURATION - 
  787.        This field specifies the length of time it will take to complete the
  788.        task.  The units of time for this field will depend upon the selection
  789.        made for the Project Calendar type in the Header Fields.  (See
  790.        Section 2.3). 
  791.  
  792.        Two fields are provided for duration here -- the Planned 
  793.        duration, which is what you thought it would take, and the Actual 
  794.        duration, which is what it did take.  Normally, in the project 
  795.        definition mode where you are adding new tasks, only the Planned 
  796.        duration would be defined.  The Actual would be left at 000 until 
  797.        that task had been completed. 
  798.  
  799.        The DURATION field is numeric only and will not accept negative 
  800.        numbers. 
  801.        
  802.        A project task with a Planned duration of 0, no start or end
  803.        date and no dependencies has a special meaning in AmiGantt.  It
  804.        denotes a 'header line' placed in the Gantt chart just to make things
  805.        more readable, separate groups of tasks, or provide additional
  806.        explanation. 
  807.  
  808.        If a Dependency is supplied for a task with duration = 0, this
  809.        tells AmiGantt that this is a Milestone.  It is recorded in the
  810.        Gantt Chart by an asterisk (*).
  811.  
  812.      DEPENDS ON - 
  813.        In this field, the user describes any other tasks that must 
  814.        be completed before this task may start.  In other words, that 
  815.        this task's start date is dependent on.  Up to ten other tasks may
  816.        be defined in this way and their task numbers should be placed in
  817.        the DEPENDS ON field, separated by spaces or commas.  (e.g. 8 9 10
  818.        or 8,9,10) 
  819.  
  820.        Version 3.0.0 of AmiGantt and above support 'calculated dependencies'.
  821.        In this case, you can specify that at task will begin 3 days after 
  822.        the end of another task.  Or 2 months before the start of another 
  823.        task.  To implement this feature, you simply append a '+' or a '-'
  824.        sign directly after the dependent task number, followed immediately by
  825.        the number of units (days, weeks, or months.)  The '+' sign means that
  826.        the units following are added to the end of the dependent task and
  827.        the '-' sign signifies time before the task start date.
  828.        (5+14 = 14 days after the end of task 5
  829.         17-2 = 2 months before the start of 17.) 
  830.    
  831.        As mentioned in the Start Date field above, if the Task Start 
  832.        Date is left blank and dependent tasks are defined in the 
  833.        DEPENDS ON field then AmiGantt will look at each of the 
  834.        dependent tasks -- find out which has the latest end date -- then set 
  835.        the actual start date of this task to the next day, week, or 
  836.        month after that ending date.  As far as the user will see, the 
  837.        task will still show a start date of blank but it will 'float' 
  838.        depending upon the start dates and durations of the dependent 
  839.        tasks.  The beauty of connecting tasks together this way is that 
  840.        if one task is changed, or the project start date is updated,
  841.        AmiGantt will manage and modify all the connections of tasks and 
  842.        adjust project schedule accordingly. 
  843.  
  844.      RESOURCES - 
  845.        The fields below the DEPENDS ON field allow the user to specify 
  846.        up to 10 resources (typically people doing the project) that are 
  847.        assigned to this task and the cost, on a per-unit-of-time basis, 
  848.        for each. 
  849.  
  850.        The Title fields (right below the RESOURCES: description) are 15 
  851.        characters long, will accept any alphanumeric characters, and can 
  852.        be used to provide peoples names, initials, or job descriptions.  
  853.        The Cost fields to the right of the Title fields, are numeric 
  854.        only.  They will accept up to two decimal places and even 
  855.        negative numbers (if using someone or something can actually 
  856.        reduce the project cost).  The '$' sign is unnecessary and 
  857.        invalid for this field. 
  858.  
  859.        Any or all of these fields may be left blank.  Cost fields which 
  860.        are left blank are assumed to be 0.00
  861.  
  862.        To the right of the Cost fields is a single character field marked
  863.        'F/V'.  This field is used to indicate if the cost for a particular
  864.        resource is Fixed or Variable.  If the default value of 'V' is left
  865.        in this field, then the cost of the resource is Variable and will be
  866.        multiplied by the task duration to determine the real cost.  If an 'F'
  867.        is placed in this field to specify that the cost is fixed, then there
  868.        will be no calculation and the cost is assumed to be that set value, no
  869.        matter how long the project_duration.     
  870.  
  871.        After the appropriate values have been supplied for each of the fields, 
  872.        the user should select the OK Gadget in the lower left of the window to
  873.        add the task to the project.  If the user changes his mind about adding
  874.        the task, the CANCEL gadget in the lower right of the window may be
  875.        selected    to return to the Main Screen without effecting any changes. 
  876.  
  877.        As with the Modify Header window, the user may move from field to field
  878.        down the screen by pressing the RETURN key once he/she has finished
  879.        putting the desired value in the field.  Pressing RETURN while the
  880.        cursor is in the    last Cost field will have the same effect as selecting
  881.        the OK gadget at the bottom left of the window.
  882.  
  883.      Task Types
  884.        There are three types of tasks which may be defined in an AmiGantt
  885.        project:  HEADERS, MILESTONES, and 'regular' TASKS
  886.  
  887.        HEADERS
  888.        ...are entries made into the project schedule to separate groups of
  889.        tasks or as explanatory notes.  They have no effect on the project
  890.        schedule and are descriptive only.  To insert a HEADER entry, the
  891.        Description field should be filled in with the desired information.
  892.        All the other fields (such as Start and End Dates, Depends on, 
  893.        Duration, and Resources) should be left blank.
  894.  
  895.        MILESTONES
  896.        ...are tasks which record the occurrence of a particular event on
  897.        a particular date.  Typically, they are goals to be strived for.
  898.        To define a MILESTONE, the Description field should be filled in 
  899.        with appropriate text, the Start Date field may have the desired
  900.        target date filled in, and the End Date and Duration fields should be
  901.        left blank.  As of Version 3.00.00 of AmiGantt, you can set the 
  902.        Milestone task to be dependent upon the completion of other tasks.
  903.        You may fill in Resources if you    wish, but these will not be included
  904.        in any of AmiGantt's reports.
  905.        
  906.        AmiGantt will display MILESTONES on the Gantt Chart with an 
  907.        asterisk (*) at the appropriate day.
  908.  
  909.        'Regular' TASKS
  910.        ...are defined in the normal manner, as described in the Add Task
  911.        section above.  They define tasks to be completed in the project
  912.        and have durations, dependencies (maybe), resources, start dates and
  913.        end dates.  However, the    start and end dates may be implied by the
  914.        dependencies.  (So you don't fill them in)  
  915.        
  916.        Thus, to summarize...
  917.        HEADERS -- descriptive only
  918.            -- no start date, end date, dependencies or duration
  919.  
  920.        MILESTONES
  921.            -- description and start date (or dependencies)
  922.            -- no duration
  923.  
  924.        Regular TASK
  925.            -- description and duration as minimum
  926.            -- start date may float by leaving it blank
  927.            -- if end date is left blank, it is calculated based
  928.             on start date + duration
  929.            -- dependencies may be used to determine start date
  930.            -- if dependencies are left blank, start date is assumed
  931.             to be the same as project start date
  932.            -- if a start date is provided, it is assumed to be the
  933.             earliest start date for the task
  934.            -- if an end date is provided, it is assumed to be the
  935.             latest end date for the task
  936.            -- differences between start date + duration and end
  937.             date will be shown as a 'float' period
  938.  
  939.  
  940. 2.4.1  Adding Another Project as a Task 
  941.  
  942.        AmiGantt provides a way in which other projects may be added as 
  943.        sub-projects to the project you are working on.  In other words, 
  944.        another entire project becomes a 'task' of the master project you are 
  945.        currently defining. 
  946.  
  947.        To define this sub-project, the user would set the current task block
  948.        at the desired position and select Add Task to display the Add Task
  949.        window as described in the previous section. 
  950.  
  951.        In the DESCRIPTION field, instead of putting some text about the task 
  952.        to be completed, the user should put in two slashes ('//') right at
  953.        the left-most edge of the field, followed by the volume, directory(ies)
  954.        file name, and extensions of the previously saved project file, in
  955.        normal AmigaDOS format.  
  956.      
  957.        Thus the format of the description line should be -- 
  958.  
  959.              //volume:directory/file.extension 
  960.  
  961.        E.g. if there is another project file I want to add as a sub-project in 
  962.        file 42X in directory RNDPROJ on volume FRODO, the description line 
  963.        should look like -- 
  964.  
  965.              //frodo:rndproj/42x 
  966.  
  967.        Note that the entry is case-independent (as is normal for AmigaDOS
  968.        convention), i.e. it doesn't matter if you type in upper or lower case 
  969.        letters. 
  970.  
  971.        Although you can specify a start date if you wish to tie it to a 
  972.        particular date, this field and the rest may be left blank.  When the 
  973.        entry is added, AmiGantt will examine that project file determine the 
  974.        starting date and duration of the entire project and copy all the 
  975.        resources from the project file (up to the 10 maximum for a task) into 
  976.        this task entry. 
  977.  
  978.        If the start of this sub-project is dependent upon completion of other 
  979.        tasks or sub-projects, these task numbers should be filled into the 
  980.        DEPENDS ON field before selecting the OK gadget to add the task. 
  981.  
  982.  
  983. 2.4  Modifying Tasks 
  984.  
  985.        We all make mistakes or change our mind about something, so if the 
  986.        information within a particular task needs to be altered, or possibly 
  987.        an actual duration needs to be added, the user may position the current 
  988.        task block over the task he wishes to change and select Modify Task
  989.        from the Task Menu.  After doing so, AmiGantt will present the Modify
  990.        Task window. 
  991.  
  992.        Note that this looks very similar to the Add Task screen mentioned 
  993.        previously, with all the fields in the task modifiable.  The difference 
  994.        here will be that the various fields will display the existing values 
  995.        for that task and the window name at the top left corner of the window 
  996.        will specify the MOD Entry action. 
  997.  
  998.        Keeping in mind the same restrictions on data types for each of the 
  999.        fields as was mentioned in the Add Tasks section of this document, the 
  1000.        user may modify the contents of any field in the task.  Values of 
  1001.        fields may be set to zero or blank by simply erasing the value in the 
  1002.        field. 
  1003.  
  1004.        Once the appropriate fields have been changed, select the OK gadget in the
  1005.        bottom left of the window to record the changes to the task.  AmiGantt will
  1006.        then update the task, and update the complete project schedule with the
  1007.        new information. 
  1008.  
  1009.        Note, that if changes are made to the project dependencies, it could 
  1010.        take a second or two for AmiGantt to rearrange all the pointers and 
  1011.        reset the various floating start dates.  AmiGantt will tell you it is 
  1012.        working on these pointers, etc. by changing the mouse pointer to a
  1013.        picture of a wristwatch.  This signifies a 'Please Wait' condition and
  1014.        the user    should wait until the pointer resumes it's normal shape
  1015.        before proceeding.
  1016.  
  1017.        If you decide that you didn't really want to change this task, simply 
  1018.        select the CANCEL gadget in the lower right of the window to return to
  1019.        the Main Screen without effecting any changes. 
  1020.  
  1021.   
  1022. 2.5  Deleting Tasks  
  1023.  
  1024.        Tasks can be removed from the project by positioning the current task
  1025.        block over the task to be removed and selecting Delete Task from the
  1026.        Task Menu.  When Delete Task is selected, AmiGantt will present the
  1027.        user with the Delete Task window. (Which looks suspiciously similar to
  1028.        the Add Task and Modify Task windows). 
  1029.  
  1030.        If the user decides this is, indeed, the task he wishes to delete, he 
  1031.        should select the OK gadget in the bottom left of the window to confirm
  1032.        the removal.  If he decides otherwise, selecting the CANCEL gadget in the
  1033.        lower right will return him to the Main Screen with no changes. 
  1034.  
  1035.        Once a task has been deleted, AmiGantt will go through all the other 
  1036.        tasks in the project and remove any dependencies upon the deleted 
  1037.        tasks.  If another task was dependent only upon the deleted task, then 
  1038.        its dependency will revert to the project start date.  Since all the 
  1039.        tasks after the deleted tasks are automatically renumbered, AmiGantt 
  1040.        will also examine tasks after the deleted task to adjust their 
  1041.        dependencies. 
  1042.  
  1043.  
  1044.  
  1045. 2.6  Saving the Project (Save Project or Save As Project) 
  1046.  
  1047.        Once the project has been completely defined and all the tasks have
  1048.        been entered, it would be wise to save the project to a permanent
  1049.        storage file on disk.  Then, the project may be retrieved for update
  1050.        at a later time or included as part of a bigger project, as outlined
  1051.        in section 2.4.1. 
  1052.  
  1053.        To save the contents of the project to disk, the user selects either
  1054.        Save or Save As from the Project Menu.  For a new project, the user
  1055.        should select the Save As option which will allow him/her to create a
  1056.        new file and supply a name for the project file.  If the project was
  1057.        loaded from a previously created file, the Save option may be selected
  1058.        to overwrite the file with the new changes.
  1059.  
  1060.        Assuming we are creating a new project and the Save As option is
  1061.        selected, AmiGantt will display a file requestor window in which the
  1062.        user may either select an existing file or provide the name of a new
  1063.        file to be created.
  1064.     
  1065.        The requestor supplied in version 3.00.00 of AmiGantt and above is
  1066.        produced by the ARP (AmigaDos Replacement Program) library functions
  1067.        attached to AmiGantt and includes some new features not normally found
  1068.        on file requestors.
  1069.  
  1070.        The list of files shown defaults to the current directory from
  1071.        which AmiGantt was run.  As before, the filenames may be selected
  1072.        by clicking on them with the left mouse button.  The scroll bar
  1073.        at the right of the requestor box will move through the sorted
  1074.        filename entries.  Once the filename you wish is displayed, you may
  1075.        click on it, then on the OK box to select it.
  1076.  
  1077.        One of the added features of the ARP requestor is the ability to
  1078.        change the list to display the available devices by pressing the 
  1079.        right mouse button.  Then you may navigate through the directories
  1080.        of any device simply by clicking (with the left mouse button) on
  1081.        the directory shown.  You can return back up one level by 
  1082.        clicking on the 'Parent' button or redisplay the list of devices
  1083.        by re-pressing the right mouse button.
  1084.  
  1085.        In Save As mode, the filename box of the requestor is auto-selected
  1086.        so you can begin typing in the name for your new file as soon as
  1087.        the requestor appears -- instead of waiting for it to complete
  1088.        the display of the directory.
  1089.      
  1090.        The user should supply the name of the file, directory, and volume he
  1091.        wishes to save the project in.  It's a good idea to use a suggestive
  1092.        name for the project file name, since it will then make it easier to
  1093.        remember    for later retrieval and will make more sense if the file is
  1094.        included as a sub-project to some other, larger project. 
  1095.  
  1096.        Naming conventions for project files follow the standard AmigaDOS file 
  1097.        conventions.  Once the appropriate information has been supplied the 
  1098.        user selects the OK gadget to write the project out to the file.  If a 
  1099.        file by that name already exists, AmiGantt will notify the user and 
  1100.        give him a chance to decide whether he wishes to overwrite the existing 
  1101.        file or not. 
  1102.  
  1103.        If the user wants to overwrite the existing file, he should select the OK
  1104.        gadget in the lower left of the requestor box.  AmiGantt will then
  1105.        erase the contents of the existing file and replace them with the new
  1106.        project file. 
  1107.  
  1108.        If instead, he wishes to keep the existing file and provide a new file
  1109.        name for the project, he should select the CANCEL gadget in the lower
  1110.        right of the requestor box.  AmiGantt will then return to the main
  1111.        screen, without making any changes. 
  1112.  
  1113.  
  1114.  
  1115.                     AmiGantt -- Project Management Software 
  1116.  
  1117.  
  1118.                             3.0  Printing a Project 
  1119.  
  1120.  
  1121. 3.1  Printing a Screen 
  1122.  
  1123.        From the Main Screen, the contents of a displayed screen can be dumped 
  1124.        out to the user's default printer device (PRT:) by selecting Screen
  1125.        from the Print menu.  After selecting this option, AmiGantt will
  1126.        display the PIP (Printing in Progress) pointer and a graphic dump of
  1127.        the screen on display will be sent to the printer.  Due to the manner
  1128.        in which AmigaDOS accomplishes this dump, the user should avoid making
  1129.        changes to the screen while the printout is proceeding.
  1130.  
  1131.        As mentioned earlier, if the user has selected output to a file, 
  1132.        instead of the printer, AmiGantt will generate IFF files of each of
  1133.        the windows open at the time the request is made.  The files created
  1134.        will have suffixes of _gantt.iff, _pert.iff, and _resource.iff added
  1135.        to the file name supplied.  As it is saving each of the windows, 
  1136.        AmiGantt will bring the window to the front of the display to let the
  1137.        user know what is going on.
  1138.  
  1139.  
  1140. 3.2  Printing the Project 
  1141.  
  1142.        Printing out the contents of an entire project via screen dumps would 
  1143.        not be the most economical nor useful method of seeing the project as
  1144.        a whole, so AmiGantt provides a Project Print function which will
  1145.        provide a number of different reports about the project.  Included in
  1146.        these reports are the following -- 
  1147.  
  1148.     a) GANTT chart 
  1149.         b) Task List and Summary 
  1150.         c) Resource Summary 
  1151.         d) Resource Histogram
  1152.         e) Pert chart 
  1153.  
  1154.        Each of these reports are discussed in more detail below. 
  1155.  
  1156.        To generate these reports, the user selects Project from the Print
  1157.        Menu.  AmiGantt will change the mouse pointer to the PIP (Printing in
  1158.        Progress) picture while it is generating the reports.  It will return
  1159.        to the 'normal' pointer when the report is completed.  Version 3.00.00
  1160.        and above of AmiGantt will then check the Preference settings for your
  1161.        printer to determine if they are suitable for the reports.  They
  1162.        should be set at:
  1163.         a) 15 pitch, if you have narrow tractor paper
  1164.             b) a left margin of 8 or less
  1165.       and   c) a right margin of at least 140
  1166.  
  1167.        If any of these are not correct, AmiGantt will present a 
  1168.        requestor asking if you wish to have AmiGantt send the correct 
  1169.        sequences to the printer to set it up.  If you select OK, AmiGantt
  1170.        will use the driver selected in Preferences to send the appropriate
  1171.        escape sequences to set the pitch and the right margin.
  1172.  
  1173.        At any time during the printing of the reports, the user may stop
  1174.        the printing by pressing the ESC key on the keyboard.  If the
  1175.        printer has a large data buffer though, the printout may continue
  1176.        for a short time after the ESC key has been pressed.
  1177.  
  1178.        For the Gantt Chart, Pert Chart and Resource Histogram, two types of 
  1179.        printout are available -- selected by the Type option of the Print 
  1180.        menu.  The GRAPHIC option, which is the default, provides high quality
  1181.        bit-map grpahic printouts on printers that can support this output.
  1182.        It uses the graphics options of the printer driver specified in the
  1183.        Preferences program (such as graphic density and orientation).  Note,
  1184.        AmiGantt creates only black and white output.  It does not produce 
  1185.        colour printouts.
  1186.  
  1187.        The second option is the TEXTUAL, which produces ASCII-character based
  1188.        representations of the Gantt, Pert, and Resource charts (much as in
  1189.        earlier versions of AmiGantt.  This option should be selected if your
  1190.        printer does not support bitmap graphics printing.
  1191.  
  1192.  
  1193. 3.2.1  Gantt Chart 
  1194.  
  1195.        As outlined in the Introduction section of this manual, AmiGantt 
  1196.        was designed around the Gantt Chart model in order to provide a simple, 
  1197.        top-down interface in the definition and management of projects.  The 
  1198.        main screen interface and printouts of AmiGantt are simplified Gantt 
  1199.        Chart representations.
  1200.  
  1201.        On the Gantt Charts, tasks are displayed using an extended shaded bar
  1202.        to show the start date and duration of the task.  'Float' periods
  1203.        between the last day of the duration and a 'latest end date'
  1204.        established when    the task was added, are shown by a hollow bar
  1205.        positioned after the duration bar.
  1206.  
  1207.        Milestones are shown on the chart using asterisks (*).
  1208.  
  1209.        Actual Durations of tasks are shown using a filled bar, printed over
  1210.        the planned shaded bar.
  1211.  
  1212.        In the report printouts provided by AmiGantt, the Gantt chart will
  1213.        show the entire project (or as much of it as possible) on a single
  1214.        page.  If the project should go beyond either 60 tasks (the vertical
  1215.        limit) or dates shown on the printout calendar (depends on the type
  1216.        of project calendar) then AmiGantt will generate a new page of
  1217.        printout to cover the next portion of tasks or calendar.  These extra
  1218.        pages are generated in such a way so that the entire project can be
  1219.        'glued together' into one master sheet by attaching additional date
  1220.        sheets to the right of the first page and task sheets to the bottom
  1221.        of the first page. 
  1222.  
  1223.        On the Gantt Chart, project task numbers are shown on the left side, 
  1224.        followed by the complete description.  The task start date and duration 
  1225.        are then plotted on the project calendar.  Those tasks which are not 
  1226.        completed (no actual duration provided) are shown in light arrows.  
  1227.        Completed tasks are shown as dark blocks. 
  1228.  
  1229.        An example of the Gantt Chart printout is provided in section 5.0 of 
  1230.        this manual. 
  1231.  
  1232.   
  1233. 3.2.2  Task List & Summary 
  1234.  
  1235.        The next report prepared by the project printout function is the
  1236.        detail task list and summary. 
  1237.  
  1238.        The detail task list shows every task that has been defined for the 
  1239.        project and all information provided for each task.  This report
  1240.        should be used mainly to verify input and dependencies. 
  1241.  
  1242.        The task summary report provides a shorter, less detailed look at the 
  1243.        tasks in the project with additional information regarding planned and 
  1244.        actual costs of the tasks and the entire project. 
  1245.  
  1246.        Beside each task description, the start and end dates of the task are 
  1247.        shown.  If the dates shown are for actual start and end (i.e. actual 
  1248.        duration has been provided), an '(A)' will be placed beside each of
  1249.        the dates.  If they are planned start and end, a '(P)' will be placed
  1250.        beside each date. 
  1251.  
  1252.        Next to the start and end dates for each task is the planned and
  1253.        actual cost of each task.  The numbers presented here are calculated
  1254.        by AmiGantt from the planned and actual durations and the costs for
  1255.        each of the resources identified for each task.  These Plan and Actual
  1256.        Costs for the tasks are totalled at the bottom of the page. An example
  1257.        of the task detail list and task summary are provided in section 5.0
  1258.        of this manual. 
  1259.  
  1260.  
  1261. 3.2.3  Resource Summary 
  1262.  
  1263.        The AmiGantt printouts also provide a resource summary listing which 
  1264.        shows all of the resources that have been committed to the project,
  1265.        the planned and actual time commitment of each of those resources,
  1266.        and the planned and actual costs of the resources during the duration
  1267.        of the project. 
  1268.  
  1269.        AmiGantt generates this listing by examining each task in the project 
  1270.        and collecting information on each resource defined.  The cost 
  1271.        information is gathered by collecting the cost for each resource in a 
  1272.        task and multiplying it by the planned and actual duration of the task. 
  1273.  
  1274.        At the bottom of the page, the total commitment and costs for the 
  1275.        project are totalled for comparison with the total costs provided on 
  1276.        the Task Summary report mentioned earlier. 
  1277.         
  1278. 3.2.4  Resource Histogram 
  1279.  
  1280.        The Resource Histogram produced by AmiGantt is useful in determining 
  1281.        when resources will be required for various stages of the project and 
  1282.        when double-ups occur on a given resource.  Frequently, when defining a 
  1283.        project, it is difficult to see when a given person or physical piece 
  1284.        of hardware is expected to be in two places at the same time.  The 
  1285.        Resource Histogram, with its overall view of the project from a time 
  1286.        vs. resource basis, quickly shows these inconsistencies. 
  1287.  
  1288.        An example of the Resource Histogram produced by AmiGantt is shown in 
  1289.        section 5.0. 
  1290.  
  1291.  
  1292.  
  1293.  
  1294.                     AmiGantt -- Project Management Software 
  1295.  
  1296.  
  1297.                        4.0  Modifying Existing Projects 
  1298.  
  1299.  
  1300. 4.1  Loading the Project 
  1301.  
  1302.        As mentioned in section 2.1, once a project has been defined and saved, 
  1303.        it can be easily retrieved for modification or update by selecting the
  1304.        Load option from the Project Menu.  Once this option has been selected,
  1305.        a file requestor will be presented to allow the user to select and/or
  1306.        define the name of the project file to be loaded.
  1307.  
  1308.        In this requestor, the user should fill in the file name, directory,
  1309.        and volume on which a previously defined project file has been stored.
  1310.        The user should fill in the appropriate information, then select the
  1311.        OK gadget to request loading of the project.  As mentioned before,
  1312.        this requestor is generated by the ARP library and hence has the
  1313.        additional capability of displaying a list of all devices by pressing
  1314.        the right mouse button.  The user may then navigate the directories of
  1315.        any device using the left mouse button and the scroll bar. 
  1316.  
  1317.        AmiGantt will check for the existence of the file and if it is not 
  1318.        found will present an error message and give the user another chance
  1319.        to define the project file. 
  1320.  
  1321.        If the file does exist, AmiGantt will also check the internal
  1322.        structure of the file to determine if it is, indeed, a AmiGantt file. 
  1323.        If it is not, the user will be notified via an error message and given
  1324.        the opportunity to define another file. 
  1325.  
  1326.        If the user wishes not to load a project file, or cannot find the 
  1327.        existing project file, then he can select the CANCEL gadget from the
  1328.        file requestor to  return to the Main Screen. 
  1329.  
  1330.        After successfully defining an existing AmiGantt file and selecting
  1331.        the OK gadget, AmiGantt will read the file, load in all the tasks, and 
  1332.        return the user to the Main Screen which has been updated with the 
  1333.        first 20 tasks and their calendar mappings.  At the same time,
  1334.        AmiGantt will also load the previously defined header information and
  1335.        will change its calendar display to match the header entry. 
  1336.  
  1337.        At this point, the user is free to change the project as desired or
  1338.        produce printouts of the project. 
  1339.  
  1340.   
  1341. 4.2  Modifying the Header Information 
  1342.  
  1343.        Once an existing project has been loaded, the user may choose to
  1344.        change any or all of the information in the tasks or to add new tasks.
  1345.        He may also wish to change any of the information in the Project
  1346.        Header.  As mentioned in section 2.3, the project header information
  1347.        may be accessed by selecting the Modify Header option on the Task Menu.
  1348.        In the case of 'loaded' projects, this screen will now display the
  1349.        header information provided when the project was created or last
  1350.        modified.  The user may choose to change any of the information in
  1351.        this header, and select the OK gadget to record the changes. 
  1352.  
  1353.        If the user changes the project calendar, a message will be presented 
  1354.        at the top of the screen, asking if the project tasks should be
  1355.        converted to the new base.
  1356.  
  1357.        If the user selects the NO gadget at the lower right of the requestor
  1358.        box, AmiGantt will change the project calendar, the calendar display
  1359.        on the Main Screen, and assume that all duration entries in the tasks
  1360.        should be converted directly to the new calendar base.  In other words,
  1361.        if the previous calendar base was D for Daily, and the user changes
  1362.        the project calendar to M for monthly and says NO to the conversion,
  1363.        then a task duration that was originally 2 days will become 2 months.
  1364.        Similarly, a task resource that used to have a cost of $100 per day,
  1365.        will now have a cost of $100 per month. 
  1366.  
  1367.        Selecting the OK gadget will cause AmiGantt to convert the task
  1368.        durations from the original calendar base to the new calendar base
  1369.        using the rules outlined below. 
  1370.  
  1371.  
  1372. 4.2.1  Conversion of Costs/Durations 
  1373.  
  1374.        Original Base     New Base          Conversion Factor
  1375.        -------------     --------       -------------------- 
  1376.          Daily            Weekly           Divide duration by 5 
  1377.                                            Multiply cost by 5 
  1378.  
  1379.          Daily            Monthly          Divide duration by 22 
  1380.                                            Multiply cost by 22 
  1381.  
  1382.          Weekly           Daily            Multiply duration by 5 
  1383.                                            Divide cost by 5 
  1384.  
  1385.          Weekly           Monthly          Divide duration by 4 
  1386.                                            Multiply cost by 4 
  1387.  
  1388.          Monthly          Daily            Multiply duration by 22 
  1389.                                            Divide cost by 22 
  1390.  
  1391.  
  1392.  
  1393.  
  1394. 5.0  Enhancements to version 2.02.00 of AmiGantt 
  1395.     and known anomolies
  1396.  
  1397. 5.1  Enhancements
  1398.  
  1399. a)  The file structure used to store AmiGantt project information has been
  1400.     expanded.  This unfortunately means that projects created with version
  1401.     1.01.00 or 1.01.01 of AmiGantt cannot be used in AmiGantt 2.01.00 and
  1402.     above.
  1403.  
  1404. b)  AmiGantt 2.02.00 now has an option under the Misc Menu to determine if
  1405.     project icons should be created under 'Save' or 'Save As' or not.
  1406.     
  1407. c)  AmiGantt 2.02.00 will not crash if arp.library is not in the LIBS: 
  1408.     directory.  If ARP is not available, a plain vanilla file requestor is
  1409.     substituted for the ARP requestor.
  1410.  
  1411. d)  All the 'Not Ready Yet' window code has been removed.  Features not 
  1412.     implemented are now 'ghosted' on the menus.
  1413.  
  1414. e)  The Gantt Window will now size itself properly to any screen dimension
  1415.     (interlace, non-interlace, MoreRows, etc.) and any default system font.
  1416.     The Resource Window may still have some problems though, if the font is
  1417.     not 8 point.  
  1418.  
  1419. f)  A new sort option, Critical Path, has been added.  In this option, 
  1420.     AmiGantt will examine all the tasks in the project, determine those that
  1421.     are on the Critical Path (going from start to end and taking the longest
  1422.     time) and will rearrange those to be shown at the top of the list.
  1423.  
  1424. g)  The right and left cursor keys will now scroll the Gantt Window display
  1425.     forward and backward one week at a time.
  1426.  
  1427. h)  Thanks to a new feature of Blink from Lattice, the 'stdout' window
  1428.     created when running from Workbench has been eliminated.
  1429.  
  1430. i)  A new menu item has been added, MISC, which contains an entry for turning
  1431.     on and off the creation of icons for Save Project.
  1432.  
  1433.  
  1434.  
  1435. Known Anomolies
  1436.  
  1437.  
  1438.  
  1439.